Tight schedule moving heavy generators no problem for Harbor Freight Transport at the Port of Newark

By: | at 12:55 PM | Channel(s): Breakbulk & Projects  

​After having been stored in-bond for about one year all five units needed to be transported and loaded onto an ACL vessel, located at Berth 17 in the Port of Newark. The challenge was that we were only given two days’ notice and the experts from Harbor Freight Transport only had three days to complete the job.The cargo consisted of 5 Generators for Rolls Royce; 30’ long, 16’ wide and 11’ high; 220,000 lbs each and additional 500,000 lbs of miscellaneous cargo