Service Name | Service Code | Vsl Code - Vessel Name - Voy | Contingency Plan / Cargo Rerouting |
MAE | U7B | T51 - FRISSIA LISSABON - 1715 | IMPORT into USHOU cargo will discharge in MXALT and load on the F8F March 1711 ETA 9/2 and discharge in USHOU ETA 9/4. (7 day delay) EXPORT out of USHOU cargo will load on next weeks vessel D1T Buxlink 1717 ETA 9/4. (7 day delay) |
ACX | U4A | PU3 - BARRY - 1707 | Imports into USHOU: Will now be discharged in USNOL and terminated at USNOL. Exports ex USHOU: Will be rolled to the next vessel/voyage. +7 day delay |
ACX | U4A | D74 - ANGOL - 1711 | Imports into USHOU: Will now be discharged in MXALT and connect to the F8F-March from MXALT to USHOU. +7 days delay Exports ex USHOU: Will be rolled to the next vessel/voyage. +7 day delay |
TA1 | 821 | 027 - MAERSK OHIO - 734E | Import into USHOU: Maersk Ohio will be induced to Freeport (BSFPOPT) to discharge USHOU imports that are already on board the vessel. Units to connect at BSFPOPT to the MAERSK DENVER (7KC-1709), + 7 days delayed. Exports ex USHOU are being rolled to the MAERSK KENTUCKY 735E, +7 days delayed |
GULFEX | UHA | 6HZ - MSC LUDOVICA - 1711 | Vessel Omitting USHOU. All import cargo on 1710 will discharge in USNOL10. All export cargo on the 6HZ MSC LUDOVICA 1711 exiting USHOUTM will load on the 00N E.R. CANADA 1711 etd: 09/12/17 |
TP18 | 758 | Y13 - MSC SAO PAULO - 735W | Vessel will perform a port swap, calling USMOB prior to USHOU. Imports and Exports will be delayed 7 days. |
TA6 | 646 | 06M - SEALAND ILLINOIS -733E | Vessel is omitting USHOU. Imports and Exports will be delayed 7 days. |
TA6 | 646 | 731W - MSC STELLA - 734E | Vessel will perform a port swap, calling USNOL prior to USHOU. Imports and Exports will be delayed (time subject to USHOU port reopens). As a result, this will cause delays in her schedule. All USMIAPT exports booked to the MSC Stella will be updated to the Sealand Illinois 733E. Sealand Illinois will be receiving in USMIA until FRI 9/1. |
SeaLand Hurricane Harvey update for Tuesday September 5th
posted by AJOT | Sep 05 2017 at 03:59 PM | Ports & Terminals | Liner Shipping
Demurrage & Detention
SeaLand has stopped its demurrage & detention clock between Friday, August 25th and Monday, September 4th, (inclusive), given the Port of Houston’s closure. The demurrage & detention clock will resume on Monday, September 4th, the re-opening of the terminal. Containers within freetime will have their freetime resume at that time. Containers with demurrage or detention charges will resume accruing charges at that time.
Vessel Operations:
Please see below for confirmed operational statuses of impacted vessels: