Skanska announced it has been awarded a contract by LGAFUEL LLC to carry out the $113 million construction of LaGuardia Airport’s fuel transmission systems in Queens, New York. The project will greatly improve the airport’s fuel network, creating a streamlined process to transfer fuel to and from the airport’s stationed aircraft.
The scope of the project involves the construction of 11,000 feet of two parallel jet fuel transmission lines, electrical and communication duct banks, belowground isolation valve vaults and cathodic protection systems. Additional work includes the modification of LaGuardia’s existing civil, utilities, electrical, communication duct banks and infrastructure to support the operations and maintenance of the hydrant fueling system.
The project commenced in January 2024 and is expected to reach completion in May 2026.