360 Logistics recently handled another breakbulk import of 3 x LNG tank into Fremantle, Western Australia. From under hook collection to jacking down at three remote delivery locations. Due to permit restrictions they had to travel through an approved route, extending the travel time and distance to the sites near Kalgoorlie to 1300 km and 1600 kms to Esperance, each taking about three to four travel days.