Mammoet builds on expertise in the Americas to execute a time-saving concept for one of the biggest mining companies in the world
Mammoet has completed its first dragline relocation project in Australia. The dragline, weighing 2990 metric tons, was jacked up and transported 99 kilometers on SPMTs overcoming a variety of obstacles on the way. Using experience from similar projects in the USA, Mammoet’s team safely completed the project within the deadline – saving weeks of time it would have taken for the dragline to move there using its own propulsion (‘walking’) mechanism.

CPB Contractors, a wholly owned subsidiary of Australian publicly listed company CIMIC Group Limited, were contracted to move the Marion 8050 dragline. CPB undertook all civil works and engaged Mammoet as the jacking and transport contractor for the relocation. The goal was to move the dragline from one mine to another in the coal mining Isaac Region, of Queensland, Australia, in the most efficient and economical way possible.
Prior to the transport, extensive route surveys had identified numerous challenges on the route such as a 9.5% incline and 10.0% declines, seven river and creek crossings, three railway crossings and two highway crossings. The railway crossings presented a significant potential risk to the project schedule as there was only one 24 hour window each month when the rail lines were shut down for planned maintenance, allowing the dragline operation to cross.

“We were genuinely very impressed by Mammoet’s engineering expertise and their hands-on approach.” Tom Graham, Project Manager, CPB Contractors.